Burgundy Canal - History
The history of the Canal of Burgundy is long
and complicated, from the first projects in the 17th century to the actual
beginnings of construction, the numerous strikes by the builders, to recent
political decisions concerning the financing of the canal. The barges continue
to cruise up and down the canal.
In 1607 the first act towards the
construction of the Burgundy canal was the tax placed on the local farmers to
help the financing of the canal section between Dijon and
St Jean de Losne. It was not until 1696, when
a study realized by Vauban, who considered the 5 possible routes the canal
could use to connect the rivers Saône and Yonne. There were many arguments concerning the route of
the canal, civil engineers who disagreed, local mayors who desired the canal to
pass as closely as possible, for they understood the economical importance of
the trade that would arrive, land owners wishing to sell at very interesting
prices.
A project by Mr de la Jonchere
in 1718 saw the canal with its summit at the small town of Sombernon,
the States of Burgundy charged Mr Abeille in 1724
with the mission of studying the Pouillenay valley.
He conclusions concerning the canal were given three years later. The route of
the canal was finally decided and accepted.
At the beginning of the reign of Louis XVI in
1765, the construction of the Burgundy canal began on the side of the Yonne working upstream towards the town of
Tonnerre, and a few years later the work began
on the Saône side towards Dijon. The cost of the
construction was assumed by the French State on the Yonne
side up to the limits of Burgundy, and the
Burgundy State with a subvention financed the rest of the construction.
The Yonne side of
the canal fell rapidly behind schedule, and due to poor funding the
construction of the canal halted in 1793. The state of Burgundy however, pushed
ahead and the canal was completed between the city of Dijon and the river Saône, on the 14th of December 1808 the first barges
arrived in the port of Dijon. During the revolution all work was stopped
Even with the insistence of Napoleon the 1st,
difficulties concerning the construction and the continual poor funding of the
project, the canal construction could not advance. It was not until 1822, after
a loan of 25 million francs, that the enthusiasm and courage came forth to
complete the project. On the 28th of December 1832 a barge crossed the summit
of the canal via the tunnel, and the Burgundy canal at last connected the north
of France to the south, the river Seine connected to the river Rhone.
The final part of the construction of the
Burgundy canal was the complicated and impressive tunnel, which is at the
summit. This tunnel is 3.333 kilometres long in a straight line, you must
remember that at these times 90% of the work was manual,
at its deepest section there is 48 metres of land above the tunnel. The
building of the tunnel began in 1826 and was terminated in 1832, the work was
very difficult and dangerous, and quite a few
workers lost their lives during the digging. The tunnel is ventilated by 32
wells, which climb to the surface; these were also used to assist in excavating
the earth during the digging.
The Burgundy Canal Tunnel is wide enough for
one barge to pass at a time, so a traffic system has always been used. There
was no room for a horse to tow the barge, so they crossed over the hill along the
tree alley where the wells can still be seen. Meanwhile, until a tug system was
developed, the men had to pull on a special cable and using gaffs to
bring the barge through. The first tug arrived on the canal in 1867, as steam
powered vessel continued to pull barges through until
1893 when an electrical tug was installed.
The arrival of the electric tug was a great progress for the canal, as it could pull five loaded
barges of 200 tonnes each or 15 empty barges. The electrical supply was
supplied by hydro-turbines located beside the two highest locks on the canal.
Here water from the canal, drove the turbines by means of a sluice gate which
generated enough power to produce 600 volts on a cable which was some 6
kilometres long. The tug drew electricity from the cable above, which powered
an electrical motor. This motor then pulled on a chain that lay on the canal
bottom, which was fixed at both extremities of the pound. The tug could then
pull the barges through. It would take between 1 and half to three hours to
make the crossing depending on the amount of boats being pulled. Although the
tug is no longer used, you can still see it if you visit the Burgundy canal as
it remains in the small town of Pouilly en Auxois.
Apart from constructing the canal, there was
also the problem of water supply, which has always been a delicate problem on
the Burgundy Canal. To enable a minimum supply of water there are the two main
rivers, on the Yonne side of the canal, the river Armancons, and the Saône side
uses the river Ouche. There are also seven
reservoirs, which assist in supplying the canal upstream from the two
rivers. In 1830 the reservoir of Grosbois was
built and terminated some 8 years later. It held more than 9 million tonnes of
water and covers more than a 100 hectares of
land, today the capacity has been reduced to 7 million tonnes. There is a
smaller reservoir below this one, which was built in 1900, covering 10
hectares, and holds under 1 million tonnes of water. The reservoir of Cercey was built in 1834, and supplies the canal with holds 3 and a half million tonnes of water,
spreading over 62 hectares. The reservoir of Panthier
was built in two stages, in 1834 and then enlarged in 1869, it holds just over 8 million tonnes of water and is 120
hectares in surface. A small reservoir called Tillot
which contains half a million tonnes over 14 hectares, and finally Chazilly built in 1830 and enlarged in 1844, which holds 5
million tonnes.
In 1879, in search to maintain an adequate
supply of water, the seventh reservoir was built, which is called the reservoir
de Pont, the perimeter is just over 12 kilometres and holds 6 million tonnes.
This may appear to be a lot of water, but one must remember that the burgundy
canal loses water each time a boat passes through a lock, as the canal uses
gravity to function, there are no pumps to push the water upstream. Water is
also lost through evaporation, leaking lock doors and on the canals dammed
stretches.
The canal also had to have lock keepers,
which were housed along the canal at the locks. Many of these houses ware built
at the same time or just after the completion to the canal. Today 99 % of the
lock houses remain, and 80% are occupied, generally by the
lock keepers. There is also the Maison Gardes, which are houses that were occupied by teams of
workers who would move along the canal to do repair work. There are also many
sluice gates along the canal, which allow the canal to overflow into the river,
where the water is held back further down stream to then be reintroduced into
the canal.
The Burgundy canal is 242.045 kilometres long
and is split into 188 pounds of water; a pound is the stretch of water between
two locks. The average length of a pound is 1287 metres,
there are 113 locks on the Yonne side of the canal
and 76 on the Saône. The canal has been built to the Freycient standard that has adopted in 1879; this required
the bridges to be lifted and the locks to be deepened. The Freycient
standard allows barges up to 38.5 metres long, 5.05 wide and a draft of 1.80
metres to navigate. The longest pound of water is 10.45 kilometres
and the shortest, 210 metres; both are on the Yonne
side of the Canal. There are also three main groups of lock with very short
pounds called staircases; the first group is from lock 1 to lock 7 on the Yonne side of the canal where the average distance is 333
metres per lock. The second more impressive group is also on this side of the
canal and is between lock 16 and 55, giving a total of 39 locks for 13.8
kilometres, an average of one lock every 350 metres. The third group is on the Yonne side, here there is an
average distance of 320 metres between locks from lock number 1 to 11.
The Canal of Burgundy
climbs 299 metres from the river Yonne and 199
metres from the river Saône to the summit.